Workspace to draw the plans

Posted by Scholeh
31
May
surPLUShome of Team Germany Solar Decathlon 2009

10 days break, where just a few legwork where done.
(From 21st till 31st of May)

If you like to see more pictures about the surPLUShome, please check our gallery aspect prefabrication.

Heroal profiles (Webcam video)

Posted by Andreas
22
May


Installing the Heroal profiles on the north side.

Put together the ceilling

Posted by Scholeh
20
May
Low build up of the ceiling with excellent wingspan.

It was a precision work to fasten the ceiling between the walls.

f you like to see more pictures about the ceiling, please check our gallery integral ceiling.

20
May

Front view:


Roof View:

15
May

The upper walls

Posted by Scholeh
15
May
Prefabrication

After the walls of the upper module are positioned they were fastened to the walls of the lower module. All walls and the base were then covered by tarpaulins, to protect them from the rain.

If you like to see more pictures about the prefabrication, please check our gallery aspect prefabrication.

Position the walls

Posted by Scholeh
14
May
Prefabrication

All lower wall elements were unloaded and mounted first unto the base. They were supported and secured by temporary braces, until the upper elements were put into place and all modules were securely fastened by our custom made steel clamps.

If you like to see more pictures about the prefabrication, please check our gallery aspect prefabrication.

09
May

Unloading the truck

Posted by Scholeh
09
May

Prefabrication
Unloading the truck with the forklift.

If you like to see more pictures about the prefabrication, please check our gallery aspect prefabrication.

Loading the walls

Posted by Scholeh
08
May
Prefabrication

The walls and the base were manoeuvred out of the production hall and loaded onto a truck.

If you like to see more pictures about the prefabrication, please check our gallery aspect prefabrication.