10 days break, where just a few legwork where done.
(From 21st till 31st of May)
If you like to see more pictures about the surPLUShome, please check our gallery aspect prefabrication.
10 days break, where just a few legwork where done.
(From 21st till 31st of May)
If you like to see more pictures about the surPLUShome, please check our gallery aspect prefabrication.
Installing the Heroal profiles on the north side.
It was a precision work to fasten the ceiling between the walls.
f you like to see more pictures about the ceiling, please check our gallery integral ceiling.
After the walls of the upper module are positioned they were fastened to the walls of the lower module. All walls and the base were then covered by tarpaulins, to protect them from the rain.
If you like to see more pictures about the prefabrication, please check our gallery aspect prefabrication.
All lower wall elements were unloaded and mounted first unto the base. They were supported and secured by temporary braces, until the upper elements were put into place and all modules were securely fastened by our custom made steel clamps.
If you like to see more pictures about the prefabrication, please check our gallery aspect prefabrication.
Unloading the truck with the forklift.
If you like to see more pictures about the prefabrication, please check our gallery aspect prefabrication.
The walls and the base were manoeuvred out of the production hall and loaded onto a truck.
If you like to see more pictures about the prefabrication, please check our gallery aspect prefabrication.